Press Enter to search
New Delhi: A major milestone has been achieved in the Rishikesh-Karnaprayag Rail Project, with Rail Vikas Nigam Limited (RVNL) completing the main excavation breakthrough of Tunnel No. 14, measuring 6.59 kilometres, in Uttarakhand's Rudraprayag district.
The breakthrough was achieved on November 27, 2026, when excavation teams advancing from both ends of the tunnel finally met, creating a continuous passage through the challenging Himalayan terrain.
The achievement marks the culmination of extensive efforts by engineers, technical experts and construction teams working under difficult geological conditions.
Excavation progressed from two ends of the tunnel. A stretch of 4.7 kilometres was excavated from the Sumerpur end, while 1.79 kilometres was completed from the Maroda end. Teams and machinery advancing from both directions eventually connected to achieve the breakthrough.
One of the biggest challenges at the first end was the loose soil and the presence of residential areas above the proposed tunnel. Excavation had to be carried out with extreme caution beneath a soil cover of just 20 to 30 metres.
The tunnel section involved a stretch of approximately 110 metres being constructed for three railway tracks. To ensure stability, engineers strengthened the ground before excavation and adopted a phased construction method involving several smaller tunnels.
At the Maroda end, the steep mountain slope and ground subsidence made construction difficult. Engineers stabilised the area using micro-pile structures extending 30 to 35 metres deep, rock bolts measuring 15 to 20 metres and specialised grouting techniques.
Only after these measures were completed could excavation of the main tunnel begin in March 2024. Challenges related to ground subsidence, land acquisition and the acquisition of houses were also addressed during the process.
The safety of nearby villages and residential buildings remained a key priority throughout construction.
At the second end, excavation was carried out using machinery along a stretch of approximately 100 metres. Controlled blasting near both tunnel portals was restricted to daytime hours to minimise inconvenience to local residents.
A special ventilation system was also installed during the excavation of the 4.7-kilometre section from the first end to ensure workers received fresh air and suitable temperatures inside the tunnel.
The breakthrough is more than just a construction achievement. It represents a significant success for modern engineering, technology and human determination in the difficult Himalayan region.
With this milestone, the Rishikesh-Karnaprayag Rail Project has moved another step closer to fulfilling the long-awaited dream of bringing railway connectivity from Rishikesh to Karnaprayag.